Cutler Bay is building a 16-acre civic campus on Old Cutler Road, backed by a $37 million voter-approved bond and millions more in federal and local funds.

The Town detailed the full financing and construction timeline for Legacy Park and Municipal Complex in a Nov. 3 press release. The announcement followed an Oct. 23 groundbreaking ceremony led by Mayor Tim Meerbott.

Four funding streams support the project. The largest is the $37 million General Obligation Bond approved by voters in 2022. More than $12.8 million in federal American Rescue Plan Act (ARPA) dollars and Town reserves is paying for arsenic removal from the site. The Town Council also authorized a Capital Improvement Revenue Bond of up to $17 million to supplement the voter-approved bond and fund the pool facility. More than $1.5 million in Voluntary Cleanup Tax Credits through the Florida Brownfields program will help offset the remediation costs.

What's getting built

The campus will include 12 acres of park space, a community center, a pool complex and a three-story Town Hall. The 32,192-square-foot Town Hall will hold a 146-seat Council Chamber and serve as an Emergency Operations Center built to withstand Category 5 hurricanes and 175-mph winds.

A 12,199-square-foot community center will have multipurpose rooms, a dance studio and activity rooms. The pool complex will feature seven swimming lanes, a shallow area and sufficient depth for water polo. The campus will also include space for farmers' markets, performances and family activities.

Construction timeline

Construction is underway.

Underground infrastructure work, including stormwater drainage, sewer, water and electrical utilities, is scheduled for completion in May 2027. The Town Council approved the next phase covering buildings, pool facilities, park improvements and landscaping.

The Town is prioritizing opening the community center and pool in late 2027 or early 2028. Full project completion is targeted for summer 2028.

How the land was secured

The site, a parcel locals call the "Potato Field," sits north of Southwest 212th Street and east of Old Cutler Road. The Town acquired it through a land swap completed in 2020 with GCF Investments Inc.

Cutler Bay traded its six-story office building at 10720 Caribbean Blvd., valued at $14 million, plus $3 million in cash for the 16 acres, valued at $17 million. The swap headed off potential residential development on the parcel. The Town's groundbreaking release described it as "more than 480 multifamily units," while a 2022 bond announcement said the zoning permitted "up to 480 residential units."

The old Town Hall building had been costing the Town about $750,000 per fiscal year in losses from low tenant occupancy and maintenance.

A second try at the bond

An initial $40 million bond referendum failed in 2018. The Town then expanded public outreach, partnering with the University of Miami School of Architecture on conceptual plans. More than 23 public meetings and over 900 resident comments shaped the revised proposal.

In a March 2022 mail-in election, the reduced $37 million bond passed with 65.84% support. Of 28,840 registered voters, 19.68% returned ballots. The bond is being repaid through a property-tax increase the Town estimated at an average of about $89 per year for homeowners over 30 years.

Meerbott recognized former Mayor Peggy Bell and the previous Council for advancing the project at the Oct. 23 ceremony. He also thanked the Garcia family for sharing the Town's vision for the site.

Miami-Dade County Commissioner Danielle Cohen Higgins and Vice Chairman Kionne McGhee joined the ceremony alongside Town Manager Rafael Casals, the design team from Saltz Michelson Architects and Michael Graves, and builder Kaufman Lynn Construction. Residents can follow construction progress at cutlerbay-fl.gov/legacypark.